A 40 × 12 ft driveway paved 3 inches thick takes about 8.8 tons of hot mix asphalt once it is rolled: 53.3 square yards × 3 inches × 110 lb per square yard per inch = 17,600 lb. With 5 % for waste and uneven base, plan on about 9.2 tons. The calculator above does the same for any area and thickness, and also figures cold patch bags for repairs and asphalt millings for a recycled driveway.
How the calculator works
Enter the length and width, or the area, and the compacted thickness. Choose hot mix, cold patch or millings. The result is the tons to order, the cubic yards, the area and the truck loads; for cold patch, the number of 50 lb bags. If you already know the tons from a quote, use the weight mode to see the area or volume it covers.
Tons of hot mix
Paving plants sell asphalt by the ton. The usual conversion in state DOT paving specifications is 110 lb per square yard per inch of compacted thickness. In other units that is 146.7 lb per cubic foot, or 3,960 lb (1.98 tons) per cubic yard. The formula is:
tons = (length × width ÷ 9) × thickness in inches × 110 ÷ 2,000
For the example: 40 × 12 ÷ 9 = 53.3 square yards; 53.3 × 3 × 110 = 17,600 lb; 17,600 ÷ 2,000 = 8.8 tons. Mixes vary a little with the aggregate, from about 140 to 150 lb per cubic foot; the plant can give you the density of the mix it ships, and the calculator accepts it.
| Compacted thickness | Tons per 100 ft² | One ton covers |
|---|---|---|
| 1 in | 0.61 | 164 ft² |
| 2 in | 1.22 | 82 ft² |
| 3 in | 1.83 | 55 ft² |
| 4 in | 2.44 | 41 ft² |
Why there is no compaction allowance
Hot mix is spread by the paver about 20 to 25 % thicker than the finished layer and rolled down. The 110 lb figure is already for the rolled layer, so you enter the finished thickness and the tons come out right. The waste allowance covers material left in the truck, hand work at edges and a base that is not perfectly flat. Millings are different: they arrive loose and are compacted on site, so the calculator adds about 20 % for them.
Truck loads
A tandem dump truck hauls about 15 tons of asphalt, a tri-axle about 18 to 20. Asphalt is dense, so the payload, not the box, sets the number of loads. Enter your plant's trucks in the delivery settings.
How thick should a driveway be?
A typical residential driveway is 2 to 3 inches of compacted hot mix on 4 to 8 inches of compacted crushed stone base. Thicker asphalt, or a two-layer pavement with a binder course and a surface course, is used for heavy trucks, soft clay soils and long-lasting work. The base matters as much as the asphalt: most driveway failures start with a thin or wet base. Figure the stone for it in the Gravel Calculator, using crusher run, which compacts hard.
Cold patch and millings
Cold patch is bagged asphalt for potholes and small repairs, sold in 50 lb bags. A bag fills about a third of a cubic foot once tamped: roughly 4 square feet at 1 inch. Fill the hole in layers of about 2 inches, tamping each. Asphalt millings, or recycled asphalt pavement, are ground-up old paving sold by the ton or yard for driveways and paths. They are cheaper than hot mix but rougher, and they compact and bind over time in the sun.
Common mistakes
- Entering the loose thickness instead of the finished one, which overorders by a fifth.
- Forgetting turnarounds, aprons and parking pads. Measure each as a rectangle and add the areas.
- Skimping on base. Two inches of asphalt on soft soil cracks in the first winter.
- Pricing by the yard. Plants quote per ton; the calculator gives both.