How it's calculated. Cubic yards = length × width × depth ÷ 27 (feet, with depth in feet), plus compaction and waste. Tons = cubic yards × density: about 1.35 tons per yard for concrete sand, 1.08 for damp masonry sand.
20' × 10' × 2" = 33.3 ft³ = 1.23 yd³ → +10 % compaction, +5 % waste = 1.43 yd³ ≈ 1.9 tons, 77 bags of 50 lb
01

How much?

Start from
ftin
ftin
in
02

Material

Coarse washed sand: concrete, paver bedding

1.35 ton/yd³Density

Typical loose value; quarries differ by 10 % or more. Use the number on your supplier's ticket if you have it.

03

Allowances and delivery

%
%
yd³
ton
Weight
1.93ton
Concrete sand · 1.35 ton/yd³ · +10 % / +5 %
Volume1.43 yd³
Area200 ft²
Volume placed1.23 yd³
Bags of 50 lb77
Truck loads1 · limited by payload
One ton covers104 ft²
Typical density; replace it with your supplier's if you have it

Density and delivery

Concrete sand · 1.35 ton/yd³ · +10 % / +5 %
DENSITY, TONS PER CUBIC YARDMasonry sand, dampFill sandPlay sandConcrete sand1.35 ton/yd³LOADS: 1 · limited by payloadDELIMETRA · FT-IN
L × W × depth ÷ 27Formula1.35 ton/yd³Density1Truck loads
Your local prices
$
$
$
$

Prices are not pre-filled: aggregate prices and delivery differ by region and quarry.

How we calculate

Volume = length × width × depth, in consistent units: feet × feet × inches ÷ 12 gives cubic feet, ÷ 27 gives cubic yards.

Weight = volume × loose density. Densities of stone, sand and soil are not standardized: they are measured per ASTM C29 and vary by quarry, gradation and moisture. The calculator starts from typical values and lets you enter your supplier's figure.

Compaction allowance adds the loose material needed to reach a compacted depth; waste covers spillage and an uneven subgrade. Neither is added when you start from a weight you already know.

Soil dug from the ground (bank volume) swells when loosened: 10 yd³ in the ground loads as about 12.5 yd³ at 25 % swell. The weight is the same; the truck volume is not.

Truck loads are limited by whichever runs out first, body volume or legal payload.

To order
1.93ton

A 20 × 10 ft patio bedded on 2 inches of sand takes 33 cubic feet, 1.23 cubic yards, of sand in place. With 10 % for compaction and 5 % for waste you order 1.43 yards, about 1.9 tons of concrete sand, or 77 bags of 50 lb if you buy it bagged. The calculator above works this out for any area, depth and sand, in cubic yards, tons, bags and truck loads.

How the calculator works

Enter the length, width and depth, an area and depth, or the volume or weight you already know. Pick the sand: concrete sand, fill sand, play sand, or masonry sand for mortar. The calculator gives the volume to order, the weight, the 50 lb bags and the truck loads.

Volume and weight

Volume is length × width × depth: feet × feet × inches ÷ 12 gives cubic feet, and dividing by 27 gives cubic yards. Weight is volume times density. Dry sand weighs about 1.3 to 1.35 tons per loose cubic yard. Damp sand behaves differently: water films hold the grains apart and the sand bulks, so a cubic yard of damp loose masonry sand weighs less, about 80 lb per cubic foot or 1.08 tons per yard, the figure NCMA uses for mortar batching. Wet sand, with the spaces between grains filled with water, is heavier again. The density on your supplier's ticket is the one to use; the calculator accepts it.

SandTypical tons per cubic yardTypical use
Concrete sand1.35Concrete, paver and flagstone bedding
Fill sand1.30Backfill, leveling, under slabs
Play sand1.30Sandboxes, washed and screened
Masonry sand, damp loose1.08Mortar (NCMA TEK 04-02A)

Compaction and waste

Sand compacts under a plate compactor or when it is wetted and screeded; 10 % is a usual allowance for bedding and fill. Waste covers spillage and low spots. Play sand in a sandbox is not compacted, so set the compaction to zero there.

How much sand for pavers, a sandbox or mortar

Pavers and flagstones are usually bedded on 1 in of screeded concrete sand over a compacted stone base; joints are filled with polymeric or fine sand, which is a separate small quantity. A sandbox is commonly filled 6 to 12 in deep. For mortar, sand is the largest ingredient: one cubic foot of damp sand makes about one cubic foot of mortar, and a ton of damp sand is about 25 cubic feet. The Mortar Calculator works out the sand for a number of blocks or brick directly.

Bags or bulk

Bagged sand comes in 50 lb bags, about 0.5 ft³ each, so a ton is 40 bags. That suits a sandbox or a few repairs. For more than about half a yard, bulk delivery is cheaper. A tandem dump truck carries about 14 yd³ or 15 tons; for sand the payload is reached at about 11 yards.

Common mistakes

For the stone base under the sand, use the Gravel Calculator; to convert other materials, the Cubic Yards to Tons Calculator.

Questions

How many tons of sand are in a cubic yard?

About 1.35 tons of dry concrete sand, 1.3 of fill or play sand. Damp loose masonry sand bulks and weighs about 1.08 tons per yard (80 lb/ft³, NCMA).

How much sand do I need for a 10 × 10 sandbox?

At 12 in deep: 100 ft³, or 3.7 cubic yards, about 4.8 tons of play sand. At 6 in, half that.

How much sand do I need under pavers?

A 1 in bedding layer: 100 ft² takes 8.3 ft³, about 0.31 yd³ or 0.4 tons of concrete sand, plus 10 % for screeding and waste.

How many 50 lb bags of sand make a cubic yard?

About 54 bags of dry concrete sand (1.35 tons per yard ÷ 50 lb), and 40 bags make a ton.

How much does a cubic yard of wet sand weigh?

More than dry: water fills the spaces between the grains. Damp loose sand weighs less than dry because it bulks; saturated sand weighs considerably more. Use the supplier's figure.

How much sand is needed for mortar?

About one cubic foot of damp sand per cubic foot of mortar. For block, 1 ton of sand with 8 bags of masonry cement lays about 240 blocks (NCMA TEK 04-02A).