How it's calculated. 8 bags of masonry cement and 1 ton of sand lay about 240 concrete blocks or 1,000 brick (NCMA TEK 04-02A). By volume, Type S mortar is 1 part portland cement, ½ part lime and 4½ parts sand, and each cubic foot of sand makes about a cubic foot of mortar.
500 blocks ÷ 240 × 8 = 16.7 → 17 bags of masonry cement and 2.1 tons of sand
01

How much mortar?

Start from
Laying
pcs
02

Mortar type and materials

Mortar
17Masonry cement, 70 lb bags
Type S · Masonry cement + sand · 500 × 8 × 16 concrete block
Mortar volume52.1 ft³
Mortar sand2.08 ton · 52.1 ft³
Sand per bag of cement≈ 22 shovelfuls
Proportions per ASTM C270 (sand 3 × cementitious)

Mix by volume

Type S · 1 : 3
ONE BATCH1 partmasonry cement3 partssandDELIMETRA · FT-IN
1 : 3Proportion1 ft³ sand ≈ 1 ft³ mortarYield52.1 ft³Mortar volume
Your local prices
$
$

Prices are not pre-filled: cement, lime and sand prices differ by region and supplier.

How we calculate

Mortar types follow the proportion specification of ASTM C270, as batched in NCMA TEK 04-02A Table 2: portland cement : hydrated lime : sand by volume is 1 : ¼ : 3¾ for Type M, 1 : ½ : 4½ for Type S, 1 : 1 : 6 for Type N and 1 : 2 : 9 for Type O. Sand is three times the cementitious volume, the top of the C270 range of 2¼ to 3.

Masonry cement mortar is one part masonry cement of the matching type to three parts sand (Type N masonry cement for Type O work). Bag volumes for batching: portland cement 94 lb = 1 ft³, hydrated lime 50 lb = 1¼ ft³, masonry cement about 1 ft³ per 70 lb bag.

Yield: about one cubic foot of mortar for each cubic foot of damp loose sand (BIA Technical Note 10), so the sand volume equals the mortar volume. One ton of damp sand is about 25 ft³.

From a number of units, the masons' batch figures of TEK 04-02A Table 2 are used, waste included: 8 bags of masonry cement and 1 ton of sand lay about 240 blocks or 1,000 brick; one Type S batch (4½ ft³ of sand) lays about 46 blocks or 225 brick; one 80 lb bag of mortar mix lays about 16 blocks or 50 brick.

To order
17Masonry cement, 70 lb bags

Five hundred concrete blocks take about 17 bags of masonry cement and 2.1 tons of sand. The same blocks laid with bagged mortar mix take 32 bags of 80 lb, and with site-mixed Type S mortar 11 bags of portland cement, 5 bags of lime and 2 tons of sand. The calculator above works this out from the number of blocks or brick you are laying, or from a volume of mortar, for any of the four ASTM C270 mortar types.

How the calculator works

Start from what you know. If you know how many blocks or brick you are laying, enter the count: the calculator uses the masons' batch figures, which already include waste. If you know the volume, from a joint calculation or a specification, enter it with a waste allowance. Then pick the mortar type and how you will buy it.

From blocks or brick

NCMA TEK 04-02A Table 2 lists how many units one batch of mortar lays, for conventional 8 × 16 in block with face-shell bedding and for brick-sized units with full bedding:

One batch8 × 16 blockBrick
8 bags (70 lb) masonry cement + 1 ton sand2401,000
Type S: 1 bag portland, ½ ft³ lime, 4½ ft³ sand46225
One 80 lb bag of mortar mix1650

The figures vary with the mason, the layout and the weather; manufacturers quote slightly different yields for their mixes, for example up to 13 blocks or 37 brick per 80 lb bag. They are good for ordering, not for a joint-by-joint calculation.

From a volume

Masonry sand bulks when damp, and the cementitious materials fill the spaces between the grains, so one cubic foot of damp loose sand makes about one cubic foot of mortar (BIA Technical Note 10). The sand you need is therefore the mortar volume, and the cement and lime follow from the mix ratio. One ton of damp sand is about 25 ft³.

Mortar types and mix ratios

ASTM C270 defines four types by their proportions or by their tested properties. Under the proportion specification, sand is between 2¼ and 3 times the total volume of cement and lime; the batches below use 3, as NCMA's table does.

TypePortland : lime : sandMasonry cement : sandTypical use
M1 : ¼ : 3¾1 Type M : 3Foundations below grade, retaining walls
S1 : ½ : 4½1 Type S : 3Reinforced masonry, below grade, high wind or seismic areas
N1 : 1 : 61 Type N : 3General work above grade, brick veneer
O1 : 2 : 91 Type N : 3Interior non-load-bearing walls, repointing soft brick

For batching, a 94 lb bag of portland cement counts as 1 ft³ and a 50 lb bag of hydrated lime as 1¼ ft³. A 70 lb bag of masonry cement is about 1 ft³; check the bag, since manufacturers print the weight per cubic foot. On site, sand is measured with a shovel: about seven shovelfuls make a cubic foot, so a Type S batch for one bag of cement takes around 31 shovelfuls of sand.

Which mortar to buy

Common mistakes

To count the units first, use the Concrete Block Calculator or the Brick Calculator.

Questions

How many bags of mortar do I need for 100 blocks?

About 3⅓ bags of 70 lb masonry cement with 0.42 ton of sand, or 6¼ bags of 80 lb mortar mix, so 7 (NCMA TEK 04-02A: 240 blocks per 8 bags and a ton of sand, 16 blocks per 80 lb bag).

How many bags of mortar for 1,000 bricks?

About 8 bags of masonry cement and 1 ton of sand, or 20 bags of 80 lb mortar mix at 50 brick per bag.

What is the mix ratio for Type S mortar?

1 part portland cement, ½ part hydrated lime and 4½ parts sand by volume, or 1 part Type S masonry cement to 3 parts sand.

What is the mix ratio for Type N mortar?

1 part portland cement, 1 part hydrated lime and 6 parts sand by volume, or 1 part Type N masonry cement to 3 parts sand.

How much sand do I need for a bag of cement?

For Type S, 4½ ft³ of sand per 94 lb bag of portland cement, about 31 shovelfuls. For masonry cement, 3 ft³ per bag, about 21 shovelfuls.

How much mortar does a ton of sand make?

About 25 ft³ of mortar: one cubic foot of damp sand makes about one cubic foot of mortar, and a ton of damp loose sand is about 25 ft³.

Which mortar type should I use for brick veneer?

Type N for most veneer above grade. Type S for below-grade work and high wind or seismic areas, Type M for foundations and retaining walls.

How much water does an 80 lb bag of mortar mix need?

About 5 quarts per 80 lb bag, adjusted for workability (QUIKRETE Mortar Mix data sheet).